Uptown Campus – John Fallon Field & Alumni Field Turf Replacements (P-0998)

August 2020

Background and Scope

The existing turf playing surfaces on both John Fallon Field (Lacrosse) and Alumni Field (Field Hockey) are both past their useful life and were in various states of disrepair. The above referenced project includes the replacement of turf on both fields as well as the following scope:

  • Addressing grading and drainage adjacent to Fallon Field to improve stormwater control
  • Updating irrigation on Alumni Field
  • Upgrading existing fencing at both fields
  • Installation of backstop netting for Fallon Field and Casey Stadium to enhance safety

Project Timelines

Construction Start: Summer 2019 (LAX)
Planned Completion: Fall 2019 (LAX)
Construction Start: Spring 2020 (Field Hockey)
Planned Completion: Summer 2020 (Field Hockey)

Project Progress as of August 2020:

FieldTurf USA Inc. is the contractor for the project. The turf and fencing at Fallon Field, safety netting at Casey Stadium, replacement of turf and fencing at Alumni Field, and site improvements at Fallon Field are complete.

Project Photos \ Renderings:
Click the image below to start the slideshow