Elevator Renovations - Phase 3
August 2017
Background \ Overview:
The overall project represents Phase 3 of the Campus Elevator Renovation Program and will address the renovation, replacement or repair of six (6) elevators/lift systems on campus. The elevators/lifts included in this project are as follows- Linear Accelerator (1970), Physical Education (1968), Draper Hall (1974), Waterbury Hall kitchen freight lift (1959), SEFCU Arena (1992), Lift in Fine Arts (1967); conversion of service keys in 18 elevators to campus standard keys.
Project Schedule \ Timelines:
Construction Start: Winter 2016
Estimated Completion: Fall 2017
Project Progress as of August 2017:
Wainschaf Associates, Inc. (Rensselaer NY) is the contractor for the project. Work to date includes:
Draper Hall:
Linear Accelerator:
Fine Arts:
SEFCU Arena:
Physical Education:
Waterbury Hall: