Physical Education and Broadview - Change in Access and Egress

Work Alert Notification

Dear Members of the UAlbany Community,

Please be advised of the following work occurring on the Uptown Campus on the north side of Physical Education. This work is necessary to support High-Temp Hot Water Underground Piping Repairs. During this time, the walkway on the north side of Physical Education will be closed from the north corner to the center of the building for X-ray testing of the welded pipe connections.

Work is expected to begin on Monday, September 21, 2026 at 2:00 PM and is expected to be completed by Monday, September 21, 2026 at 7:00 PM.
If you have any questions or concerns regarding this work, please contact the project manager, Keith Banta, at [email protected]  or at 518-442-3577.
 


Campus: Uptown Campus

Building(s): Physical Education and Broadview

Reason for Notification:

Change in access and egress
 

Estimated Start:

Estimated End:

Critical Work Description or Scope:

To complete the high-temp hot water repair, all welded connections must be X-ray tested. 

Potential Impacts on Surrounding Areas:

-    Change in access / egress


For a listing of all current Project Work Alert Notifications and notable campus projects, please view our web page.

We thank you for your continued support and apologize for any inconvenience this work may cause as we continue to renovate and upgrade the University.