Elevator Renovations - Phase 3

August 2017

Background \ Overview:

The overall project represents Phase 3 of the Campus Elevator Renovation Program and will address the renovation, replacement or repair of six (6) elevators/lift systems on campus. The elevators/lifts included in this project are as follows- Linear Accelerator (1970), Physical Education (1968), Draper Hall (1974), Waterbury Hall kitchen freight lift (1959), SEFCU Arena (1992), Lift in Fine Arts (1967); conversion of service keys in 18 elevators to campus standard keys.

Project Schedule \ Timelines:

Construction Start: Winter 2016
Estimated Completion: Fall 2017

Project Progress as of August 2017:

Wainschaf Associates, Inc. (Rensselaer NY) is the contractor for the project. Work to date includes:

Draper Hall:

  • Elevator install complete and operational
  • Contractor addressing punch list

  • Linear Accelerator:
  • Elevator install complete and operational
  • Contractor addressing punch list

  • Fine Arts:
  • Vertical conveyor machinery in place and operational
  • Contractor addressing punch list

  • SEFCU Arena:
  • Elevator is operational, however additional work still needs to be completed around hoist way doors

  • Physical Education:
  • Elevator install complete and operational
  • Contractor addressing punch list

  • Waterbury Hall:
  • Elevator install complete and operational
  • Contractor addressing punch list

  • Project Photos \ Renderings:
    Click the image below to start the slideshow